A mechanic's lien form must be recorded no later than 30 days after the
recording date of a valid notice of completion (60 days for a general
contractor), or 90 days after the date of actual completion if no valid notice of completion is recorded.
If the notice of completion that's recorded is found to be not valid, the 90-day rule applies.
To be valid, a notice of completion must be recorded within 10 days after the actual date of completion.
The notice must state the date of completion.
If the date stated is inaccurate, the notice of completion
is still valid if the actual date of completion is within 10 days prior
to the date on which the notice of completion is recorded.
For private projects, actual completion has occurred upon any one of the following:
For public projects, actual completion has occurred when the public entity accepts the work of improvement.
--
Thank you to Dave Barnier for the above information. :) Mr. Barnier is a practicing litigation attorney in San Diego CA and can be reached at 619.682.4842.
The information in this article is based upon California law current at the time of writing and is provided for general information, only. The information provided illustrates laws and legal principals in general. Any information or analysis presented in this article is intended solely to educate the reader on general issues. A comprehensive review of facts, documents, and applicable laws is always required before any attorney can competently provide any legal advice regarding any particular situation. In short: Please do not rely on any part of this article when analyzing any specific situation affecting you or your business.
California Mechanics Lien Form
Word and PDF
Instant Download
Fill-able
Save-able
Unlimited Usage!
Includes In-Depth Instructions
Construction-Business-Forms.com
Please scroll down, below the comments box, for a series of articles on mechanics lien law...
Bookmark me!
Bookmark my site and let me help you with your construction project management - together we'll crush the chaos of contracting!
Be sure to subscribe to my free newsletter to stay updated on happenings here at the site, updates to the downloadable construction forms, and ongoing news in the construction world.
Thank you for visiting and have a great day!
Diane
Lack of in-depth knowledge, or access to information, will cost you.
It can seem intimidating but really, filing the mechanic's lien is the easy part...
Can, and should, a mechanic's lien be extended?
How to prepare and serve this important document
The value of a mechanic's lien isn't always equal to the contract balance owed to the claimant at the end of the project.
California Mechanics Lien Form
Excel and PDF
Instant Download
Fill-able
Save-able
Unlimited Usage!
Includes In-Depth Instructions
Construction-Business-Forms.com
You can collect both, in different manners, but neither can be added to the mechanics lien form.
There are definite differences between them.
Contains an infographic with easy step-by-step information on how to file a mechanic's lien in Colorado.
If you record a mechanic's lien too soon you could lose all rights.
Just because you missed the deadline doesn't mean that all is lost!
The deadline is either 30 days or 90 days, depending on...
Do you have to do a preliminary notice for change orders?
Can an equipment rental company file a property lien (aka mechanic's lien)?
New! Comments
Please leave me your comments below. Facebook doesn't notify me of comments but I'm tickled when I come across them and I always respond when I see them.